Great progress this week: if not exactly raising the roof then at least pretty much finishing the roof. The slates have been fixed on the roof and the building is starting to look a bit more finished from the outside.
Continue reading “Thomas Field Hall: Raising the Roof”November Parish News Out Now
The November issue of Parish News is out for delivery. Subscribers to the print edition should be getting their copies through their letterboxes any day now.
The online edition is available on the Parish News Magazine page.
Week of Sunday 1st November, All Saints and All Souls
Services
Sunday 1st November, All Saints and All Souls
9.30 am | Great Gaddesden | Joint Parish Worship | (JR/GM-pr) |
From 3.00pm on-line | The All Souls’ service will be pre-recorded and available to view on our website from 3.00pm. During the service, candles will be lit and the names of those who have died in the last year will be read out along with the list from the 2019 service. |
The service will held in church (see the Front Page for details). It will be recorded and made available online on the Services page by lunchtime.
Continue reading “Week of Sunday 1st November, All Saints and All Souls”Thomas Field Hall: Soon to be Weather Tight
Despite some rather wet weather recently our builders are making reasonable progress and we will soon be weather tight. The heating installation, along with first fix electrical work is complete and screeding was completed on Wednesday afternoon. Roof tiling was due to start yesterday and windows are due to be fitted on 12 November.
Continue reading “Thomas Field Hall: Soon to be Weather Tight”Week of Sunday 25th October, Last Sunday after Trinity
Services
Sunday 25th October, Last Sunday after Trinity
9.30 am | Little Gaddesden | Joint Parish Worship | (JR/SO-pr) |
The service will held in church (see the Front Page for details). It will be recorded and made available online on the Services page by lunchtime.
Continue reading “Week of Sunday 25th October, Last Sunday after Trinity”Thomas Field Hall: Wrapping up Warm!
One of the major features of the building renovation is putting in insulation. We nearly wrote ‘increasing’ but in fact, there was no insulation in the original building, which explains why it was always so cold! So now there are thick insulation panels fixed to all the outside walls, all over the roofs and all over the floor. We will now be wrapping up warm: the building is literally wrapped in insulation which should keep the warmth in and make the space much more comfortable to be in, especially in winter, making our energy consumption much more efficient.
Continue reading “Thomas Field Hall: Wrapping up Warm!”Week of Sunday 18th October, Trinity 19
Services
Sunday 18th October, Trinity 19
9.30 am | Nettleden | Joint Parish Worship followed by APCM at 10.30am. We apologise if we are unable to run a live-stream of this service today on Facebook due to the unreliable signal in Nettleden. | (JR) |
The service will held in church (see the Front Page for details). It will be recorded and made available online on the Services page by lunchtime.
Continue reading “Week of Sunday 18th October, Trinity 19”Thomas Field Hall: Ambulatory Glazing Installed
This week a great step forward was made with the installation of the glazing to the Ambulatory. The glass was delivered on Tuesday. After a false start when the churchyard gates proved too narrow for the crane to get through, a smaller crane was brought to site and on Thursday the first panels started to be fixed into position.
Continue reading “Thomas Field Hall: Ambulatory Glazing Installed”Week of Sunday 11th October, Harvest Festival
Services
Sunday 11th October, Harvest Festival
9.30 am | Little Gaddesden | Joint Parish Worship for Harvest Festival | (JR/HT-pr) |
The service will held in church (see the Front Page for details). It will be recorded and made available online on the Services page by lunchtime.
Continue reading “Week of Sunday 11th October, Harvest Festival”Thomas Field Hall: Ambulatory Steelwork
The steelwork for the Ambulatory is nearly finished and painted almost completed. The lugs sticking up will carry the glass fixings which will hold the glass above the steelwork so that it will look as if it is floating. The glass is now expected to be delivered next week and then the Ambulatory will be dry and ready for the underfloor heating.
Continue reading “Thomas Field Hall: Ambulatory Steelwork”